0
Items : 0
Subtotal :  0.00
View CartCheck Out
Chennai
Chennai
Singapore
Mumbai
Switzerland
+91 44 4091 2000 Mon - Fri 09:00 - 18:30 766/1, TEZ, Sakthi Towers 1, Anna salai, Chennai 600 002.
+6584181583 Mon - Fri 09:00 - 18:30 68 Circular Road, #02-01, 049422, Singapore.
+91 98848 35702 Mon - Fri 09:00 - 18:30 5, Powai Lake Heights, Mumbai 400 072
+41 (0)91 225 81 00 Mon - Fri 09:00 - 18:30 Equvera - ISV Techno SAGL, Via Ligornetto 6A, 6855 Stabio, Switzerland
Ceritified
ISO 9001:2018
The Best
#1 in India
#1 in Europe
#1 in Asian-pacific
Number #1
AUTOMATION SOLUTION PROVIDER
Talk to an Expert
0
Items : 0
Subtotal :  0.00
View CartCheck Out

BECKMAN COULTER

Technologies Change, Customer Challenges Remain the Same

Dateline 1991: Contec enables Coulter to avoid a costly revalidation, continue production at reduced costs and support product in the field.
An unexpected end-of-life notification for a critical component left the Coulter (now Beckman Coulter) EPICS division with a major problem. The announcement came too late to buy a lifetime quantity of the component – an embedded Intel single board computer (SBC) Multibus 286 CPU for a flow cytometry analyzer. The company’s previous supplier had virtually no inventory to protect Coulter’s forward production or fulfill field service requirements. Facing a costly revalidation, Coulter didn’t have the engineering resources to search widely for a replacement part.

Industry: Medical & Healthcare
Purpose: Cost savings

Challenge

Dateline 1991: Contec enables Coulter to avoid a costly revalidation, continue production at reduced costs and support product in the field.
An unexpected end-of-life notification for a critical component left the Coulter (now Beckman Coulter) EPICS division with a major problem. The announcement came too late to buy a lifetime quantity of the component ? an embedded Intel single board computer (SBC) Multibus 286 CPU for a flow cytometry analyzer. The company’s previous supplier had virtually no inventory to protect Coulter’s forward production or fulfill field service requirements. Facing a costly revalidation, Coulter didn’t have the engineering resources to search widely for a replacement part.

Solution

Contec’s Business Development Vice President, Gene Garofalo, surveyed the market and managed to identify two potential OEMs with the same single board computer requirement and possible excess inventory. After contacting the OEMs to discuss terms and conditions, he negotiated a purchase to support Coulter’s existing production and field replacement unit requirements. In addition, expert familiarity with Multibus computer architecture enabled Contec to support warranty extensions that Coulter could offer its clients. Contec also assumed the logistics of supporting the product for future deliveries, carrying the inventory at a competitive cost.

Results

Coulter saved hundreds of thousands of dollars in revalidation costs. Coulter was able to continue delivering its product to meet customer requirements, service existing product in the field and offer warranty support. The company also reduced the cost of forward production because Contec could deliver the product as required by Coulter’s production schedule, saving on inventory costs. Said Todd Lary, Coulter Program Manager, “Contec had been aggressively offering their services, and when this EOL issue arose, Gene jumped at the opportunity and came through with flying colors.” In addition, Contec provided technical support in choosing replacement components for Coulter’s next flow cytometry analyzer, reducing the company’s required investment in engineering time. Finally, Contec’s program management services ensured a smooth product transition, allowing Coulter to remain focused on its own core competencies. “After this successful co-operative action,” said Lary, “we gave Contec more opportunities to supply us with custom embedded products, and the rest is history.”

Customer Profile

Coulter Program Manager
Todd Lary
Contec had been aggressively offering their services, and when this EOL issue arose, Gene jumped at the opportunity and came through with flying colors.